Have safety features, such as hand rails (required for decks that are 1 metre or more above ground), nonslip surfaces and adequate bracing. Check ground conditions and contour. Approach the Local Authority or Council to ascertain whether Resource and/or Building Consent is required before construction starts.
Check for any possible infringements near boundaries. For example, decks less than 1.5 metres above ground and 10 metres square may not need to go through consent procedures.
Ideally, decks are located on houses or buildings that have ready indoor/outdoor access from living areas. Determine the deck’s size and area to accommodate people and furniture. For instance, a deck that is 1.8 metres wide is the absolute minimum width to accommodate a standard table and four chairs.
 |
 |
 |
|
Handy Hints
Save effort by buying timber cut to the closest length at Mitre 10. Always remember to measure twice - cut once.
|
 |
Bracing Requirements for Decks
Any deck that projects more than 2 metres from a building requires bracing. New Zealand Standard 3604 (1999) sets out the requirements, while geographical location also has an impact on the requirements for bracing. If the deck you are planning projects more than 2 metres from the building then it is recommended that additional expert advice be sought from your Local Authority or an appropriately qualified expert.
|
BUILDING YOUR DECK
Select a datum point (a standard measurement point) - generally the existing floor level. Set the finished deck level below this datum point.
In some situations the New Zealand Building Code requires a step down to an open framed permeable deck (your Local Authority or Council will be able to advise you).
Determine a working height to set the profile boards. In this brochure, the deck profile boards are set at the top of the bearers and ledger (see diagram 1).
Identify the length of the deck along the wall of the house. From position A string a level line through to position B (see diagram 1). At points A and B drive a nail or cup hook. From each point (A and B) run a string line at right angles. The string line should be the length of the deck plus 600mm (working clearance) for profile locations.
Erect profile boards at the determined height. Set string lines for correct level and deck size (see diagram 1).
|

|
|
Check everything is square by using the 3-4-5 triangle method and equal length diagonals (see diagram 2). Do not damage string lines and check positions are consistently correct and taut.
Mark positions on existing house wall of solid framing for ledger bolt locations. Set ledger wall plate the length of A to B. Cut packers and shape to fit weatherboard or cladding angle if necessary (see diagram 3).
Lay bituminous damp proof coarse behind ledger packers. Fix ledger on packers to solid framing with 2 x M12 coach screws at a maximum spacing of 1.2 metres centre to centre (see diagram 3).
|

|
|
The New Zealand Building Code requires a minimum separation of 12mm between the wall cladding and a timber slat deck so that water will not become trapped. This separation can be provided by 12mm x 150mm long H3.2 packers at bolt fixings. Alternatively the junction between the decking and the stringer can be protected by the installation of weatherproof flashing.
Handy Hints
The 3-4-5 triangle method: to establish square, measure 300mm along one string line from the intersection where the string lines meet. Then measure 400mm along the other string line from the same point. Then measure on a diagonal between those two points. If the string lines are square, this measurement should be 500mm. If not, it will then need to be adjusted and re-measured until these measurements are correct.
|

|
|
Spacing Pile Foundations (see diagram 6)
Run a string line between pegs or from profiles at the desired depth, width and length of deck.
Locate corner piles and set out pile positions along string line and mark on the ground (see diagram 1). Piles should be spaced at maximum centres of 1.3m along the lines of the bearers and at maximum centres of 1.9m along the lines of the joists.
Dig holes with a post hole borer or a spade to a minimum depth of 450mm plus an extra 100mm for concrete pad. Clean out holes of any loose material. Place piles in holes on a concrete pad 100mm thick. Check for plumb with a spirit level and face alignment to within 1mm of string line.
|
 |
|
NOTE: Constantly check alignment is square.
Tack temporary braces to pile and ground pegs for final position. Fill holes with concrete, taking care to ensure the post is vertical. The concrete may be bagged, pre-mixed, dry concrete or a 6:1 ratio of builders mix and cement, mixed with water to a stiff mix.
Compact the concrete into the hole around piles with a stick to remove air pockets. Leave the concrete to set around piles for at least 48 hours.
|

|
|
Positioning of Bearers
The double 150 x 50 H3.2 Radiata bearers on top of the shaped head pile are to be connected to the pile with two galvanised or stainless steel post-to bearer ties on each side.
NOTE: The ‘exposed’ area on the head of the pile is trimmed at a 45 degree angle to prevent water from pooling on top.
Fix Decking Joists
Joists used in this brochure’s example are 150 x 50 Radiata H3.2, spaced 450mm apart, centre to centre. Cut joists to length and square. Leave a gap where they meet the house to allow for moisture to drain away. Skew nail bottom of joist to bearers on each side (see diagram 3).
Lay Decking
When laying decking boards, start from the furthest outer edge of the deck and work inwards. Create a 15mm setback from board edge to fascia plate. Check spacing as you go to ensure boards are square and running true to line. (Tip: Curved boards may be straightened using a suitable pry bar.) Butt boards hard up to each other to allow for shrinkage. The last board against the house may have to be scribed to fit and reduced in width.
|
 |